Capacity upgrade and ramp-up at Talnakh Concentrator

Norilsk Industrial District, Krasnoyarsk Territory
Project schedule
2015

Launch and commissioning of Stage 1

2016
  • Launch of Stage 2
  • Pilot-launched of new tailings pit
2017
  • Full commissioning of Stage 2
  • 2017 CAPEX of total project of ca. RUB 5.2 bn (USD 89 mln)
2018
  • Decision on commissioning Stage 3
  • Output of key assets of new tailings pit (first phase)

In April 2014, massive reconstruction of Talnakh Concentrator entered its main stage. In January 2015, Stage 1 was commissioned, followed by the launch of Stage 2 in May 2016. Decision on launching Stage 3 will be made in 1H 2018.

Highlights
Stage 1 Stage 2 Stage 3
  • Maintaining existing capacity at 7.5 mtpa;
  • Reconstructing existing floatation capacities and replacing flotation machines tha are beyond their useful lives and building a new tailings pit (first phase)
  • Ramping up capacity from 7.5 mtpa to 10.2 mtpa
  • Upgrading equipment;
  • Increasing nickel content in nickel-pyrrhotite concentrate from 5.8% to 9.5%;
  • Total CAPEX of ca. RUB 33.7 bn (USD 671 mln)
  • Ramping up capacity from 10.2 mtpa to 18 mtpa;
  • Building the second phase of the tailings pit.
  • Investment decision on launching Stage 3 expected in 1H 2018.