Mining projects
Increasing ore production to 5.2 mtpa by 2023 by stripping high-grade, disseminated and сupriferous ores at the Oktyabrskoye Field.
Ore reserves of | 63.0 mt |
2017 CAPEX of ca. | RUB 5.4 bn (ca. USD 93 mln) |
2018–2023 CAPEX of over | RUB 22 bn (ca. USD 371 mln) |
Average metal content
300 kt capacity commissioning
1.8 km of underground workings completed and 100 kt of new capacity completed
- Capacity commissioning (500 kt of rich ore)
- Upgrading the hoist system at skip shaft No. 3
Capacity commissioning (200 kt of rich ore)
Capacity ramp-up to 3.8 mt
Capacity commissioning (400 kt of rich ore)
Increasing ore production to 5.2 mtpa by 2023 by stripping high-grade, disseminated and сupriferous ores at the Oktyabrskoye Field.
Ore reserves of | 96 mt |
2017 CAPEX of ca. | RUB 4 bn ca. USD 69 mln |
2018–2025 CAPEX of ca. | RUB 6.0 bn (ca. USD 95 mln) |
Average metal content
- 7 km of underground workings completed,
- Capacity ramped up by 250 kt of disseminated ore and 100 kt of rich ore
Capacity commissioning (150 kt of rich ore and 700 kt of сupriferous disseminated ore)
Capacity commissioning (300 kt of сupriferous ore)
Increasing ore production to 3.8–4.0 mtpa before 2020.
Ore reserves of | 22.9 mt |
2017 CAPEX of ca. | RUB 1.2 bn (ca. USD 18 mln) |
2018–2022 CAPEX of over | RUB 14 bn (ca. USD 234 mln) |
Average metal content
- Power supply system completed at the southern ventilation shaft
- Сa. 3 km of underground workings completed
- 100 kt of rich ore capacity commissioned
- Completion of the western backfilling shaft reconstruction
- capacity commissioning (200 kt of сupriferous ore)
Capacity commissioning (175 kt of rich ore)
Capacity commissioning (225 kt of rich ore and 200 kt of disseminated ore)