Bystrinsky GOK (Chita project)
Project schedule
2017
- Naryn-1 (Borzya) – Gazimursky Zavod railway commissioned
- 220 kV power lines commissioned
- Mining and processing plant pilot-launched
- Camp for 1,047 people built
2021
Plant reaching the design capacity
Constructing an open pit and a mining and processing plant to utilise untapped reserves, constructing a railway and power lines, building a camp.
Average metal content
0,7%
23%
0,9%
| Output of | 10 mtpa |
| Ore reserves of | 333 mt |
| 2017 CAPEX of over | RUB 26 bn (ca. USD 449 mln) |
| Project CAPEX of over | RUB 89 bn (USD 1.6 bn) |
| New jobs for | 3 thousand employees |
| Cu (concentrate) | ~65 kt |
| Fe (magnetite concentrate) | 2.1 mt (Fe — 66%) |
| Au (concentrate) | 220 koz |